The Challenge
Space to host a student community of over 700 students. This will incorporate a mix of shared apartments & studio rooms, spreading over 13 floors. The site includes a gym, cinema room, karaoke room, café, laundry & much more. Space saving solutions provided include:
High output, cost effective, robust, vertical Radic Karado for the first fix of the project.
Central connections. Excellent for first fixing, 50mm centres apart.
Hertz 3000 twin body valves for all vertical radiators. Quick to install
The Solution
Hall & Common Area
This area was fronted entirely with glass leaving no wall to attach heating solutions.
Versatile provided project customised Runtal Radiators which were over 4 metres long with special welded feet to position in front of the glazed area.
Apartments & Studios
Space-saving solutions provided include:
- High output, cost-effective, robust, vertical Radik Karado for the first fix of the project.
- Central connections. Excellent for first fixing, 50mm centres apart.
- Hertz 3000 twin body valves for all vertical radiators. Quick to install